Translating part of the summary of the Japanese-language report, the “environmental preservation goals” for the plan were “evaluated to be satisfactory” in all 19 areas surveyed. These included air quality, water quality and sediment quality, soil, noise, and impacts on plant and animal life.
Osaka IRK, a corporation that develops casinos and integrated resorts (IRs) in the Japanese metropolis of Osaka, submitted an environmental impact report and a survey to local authorities in late May on the post-development.
According to the information reviewed by GGRAsia’s Japan correspondent, the review took nearly two years. 파워볼실시간
The Osaka City government is currently providing information in the form of a 69-page document.
MGM Osaka’s development consortium consists of U.S.-based MGM Resorts International and Japan’s Orix Corporation and other minority partners in Japan.
The resort, which is worth 1.27 trillion yen (currently $8.02 billion), is scheduled to open in 2030. It will be built on Yume Shima (file photo), an artificial island in Osaka Bay.
In April, Osaka IRKK announced it had signed a loan agreement worth 530 billion yen with the banking group.
The latest construction schedule includes preparation work from the first year to the third year of the development process, but the actual construction is from the end of the first year to the beginning of the seventh year.
In March this year, MGM Resorts chief executive and president Bill Hornbuckle noted that sinking the pillars at the site would likely begin in “the middle of next year” and take three years.
Construction is expected to be completed by the summer of 2030, and IR is expected to begin that fall.